Construction of a new Energy Centre continues strong partnership spanning two decades
A new low-carbon energy centre at Solihull Hospital is the latest milestone in an almost 20-year relationship with Centrica Business Solutions, helping the hospital significantly reduce its reliance on conventional heating and take another major step towards its decarbonisation ambitions.
Together with an earlier programme of energy efficiency and decarbonisation measures, the new energy centre means low-carbon heat pumps provide around 85% of the hospital’s heating requirements. The improvements are expected to reduce carbon emissions by 1,812 tonnes a year, alongside estimated annual energy cost savings of £62,000.
The new Energy Centre features a new 2MW cascade heat pump system, combining two water-source and four air-source heat pumps. This builds on a 615kW cascade heat pump system that was installed in 2024. Centrica Business Solutions is now providing ongoing operations and maintenance support for the Energy Centre, helping to maintain its performance and reliability over the long term.
Alongside these installations, Centrica Business Solutions also installed cavity wall insulation, optimised their Building Management System (BMS) and replaced of 2,500 lights with LEDs. The cavity wall installation has reduced draughts across the site, while the new LED lighting reduced eye strain. Both measures will contribute to making the site more comfortable for patients and staff alike.
The result is a significant move away from conventional fossil-fuelled heating and another major step towards the Trust’s ambition to achieve net zero for its direct emissions by 2040.
We appreciate you havent accepted cookies for our site, but if you want to watch the video you need to enable 'Targeting Cookies' and then refresh the page.
Constructing new energy infrastructure within a hospital that’s operating 24 hours a day, seven days a week required careful planning and close collaboration. The project team needed to complete major works while protecting the hospital’s day-to-day operations and minimising disruption for patients, staff and visitors. Restricted space and previously unidentified services added to the challenge.
Nonetheless, the project was completed to the highest standards of Health and Safety, with zero recordable injuries reported onsite. Solihull Hospital remained open, busy and active throughout construction, with no disruptions to patient care reported
These decarbonisation measures are the latest chapter in a relationship that began in 2005, when we installed a 750kW Combined Heat and Power unit to help meet the hospital’s demand for heat and electricity. We continued to maintain the system, helping it perform effectively and protecting its operational lifespan.
As the hospital’s needs evolved, so did our work together. In 2021, Centrica Business Solutions was invited by the Carbon and Energy Fund to competitively tender for the first phase of a new programme of carbon-reduction measures. We became the hospital’s sustainability partner for the project, and this relationship then continued into the latest project to build their new Energy Centre.
The Energy Centre is the culmination of successive projects designed around the hospital’s changing requirements: from onsite generation and long-term maintenance, through energy efficiency improvements, to large-scale low-carbon heating. It demonstrates how a long-term relationship can help an organisation progressively transform its energy infrastructure, building on previous investments and experience rather than treating each requirement in isolation.
Working with Centrica over many years has enabled us to continually improve our energy infrastructure, and this latest project will deliver significant reductions in carbon emissions and costs, while providing the heating our hospital needs. Martin Richardson Solihull Hospital, part of University Hospitals Birmingham NHS Foundation Trust
Martin Richardson, Executive Director at Solihull Hospital, part of University Hospitals Birmingham NHS Foundation Trust, said:
“The completion of the new Energy Centre is an important step in our work to make Solihull Hospital more energy efficient and reduce the carbon footprint of our estate. Working with Centrica over many years has enabled us to continually improve our energy infrastructure, and this latest project will deliver significant reductions in carbon emissions and costs, while providing the heating our hospital needs.”
The energy reduction measures were funded through the Department for Energy Security and Net Zero’s Public Sector Decarbonisation Scheme, with Salix as the delivery body and development and procurement undertaken through the Carbon and Energy Fund (CEF).
CEF supports NHS trusts and public body organisations to improve energy infrastructure and reduce overall emissions.
Andy Yates, Director of Projects at The Carbon and Energy Fund (CEF) said:
"The Carbon and Energy Fund have been proud to support University Hospitals Birmingham to deliver this exciting site wide de-carbonisation project as part of our wider strategy across the Trust.
"This successful project, funded by DESNZ and Salix under a PSDS 3c grant, delivered by our Framework Contractor Centrica Business Solutions delivers a step change for the site. Transitioning away from CHP to a cascade heat pump system to deliver carbon savings, meeting the NHS 2032 target whilst working within tight timescales, capital envelope and revenue budget."
See some of our construction photos - these show the Water Source Heat Pumps being moved into position, which form part of the 2MW Cascade Heat Pump
Through proactive operations and maintenance, Centrica Business Solutions helps Hartree Partners…
A Centrica-funded feasibility study helped Cobalt Medical Charity turn a promising sustainability…
Sloped site and harsh winter conditions didn't stop commitment to greener, fairer future for local…
Sign up to receive regular updates on:
By submitting your details you agree to process your personal data by Centrica Business Solutions as described on the Privacy Policy. Centrica Business Solutions will send you a regular newsletter and other marketing material we believe is relevant. You will be able to opt out of communications from us at any time.